top of page
Poured-In-Place Playground Surfacing System

​

Delivery, Storage & Handling

Storage and Protection: Store materials protected from exposure to harmful

environmental conditions and at a minimum temperature of 40 degrees F (4

degrees C) and a maximum temperature of 90 degrees F (32 Degrees C).

​

Project/Site Conditions

Environmental Requirements: Install surfacing system when the minimum

ambient temperature is 40 degrees F (1 degree C) and maximum ambient

temperature is 90 degrees F (32 degrees C). Do not install in steady or heavy rain.

​

Products

​

Specifier Note: The Type of playground equipment determines the required

thickness and the thickness may be different at various locations on the playground

site. Depending on ASTM F1292 requirements for critical fall height.

t-chart-template-01.jpg

Thickness  CFH

1 3/4"                          4"

​

2"                               5"

​

2 1/2"                         6"

​

3"                               7"

​

3 1/2"                         8"

​

4"                               9"

​

4 1/2"                         10"

​

5"                               12"

​

6"                               13"

Site Preparation

​

There are many different applications in which EPDM can be poured. It can

be applied over a subsurface of concrete, asphalt or crushed stone.

​

Concrete

Requires minimum thickness (which will typically be 4”) for non-weight

bearing loads per the standard. 2% slope is recommended as well as broom finish.

New concrete must be fully cured up to 2 days.

​

Asphalt

Requires minimum thickness (which will typically be 2”) for non-weight

bearing loads per the standard. A 2% slope is recommended. New asphalt must be

cured up to 30 days.

​

Crushed Stone

Stone for the base must be a homogeneous mix of .” stone down to fines

and you need to achieve a 95% compaction.

 The minimum depth of the crushed stone base is 4”. Typical thickness

ranges from 4’-6”. Crushed stone base layers thicker than 6” are more challenging

to achieve the necessary 95% compaction rate throughout the base. The thickness

must never exceed 10”.

 Crushed stone base must be fully contained.

A 2% slope is recommended.

Crushed stone is not an acceptable sub-base for any mounded area. In these

areas, in order to make it more stable, the stone would need to be skim-coated with

concrete or asphalt.

​

Note: Regardless of the base option you select for safety surfacing, proper drainage

will be critical in order for the surfacing system to last for a long time. Drainage

that is not adequate will cause premature breakdown of the poured or tile material

in affected areas and will cause the warranty to be voided.

​

Please view the pictures below to view installation process :

Edge Detail at curbs.jpg
ADA Wheelchair Accessible Edge.jpg
Flush Rolled Edge.jpg
Raised Rolled Edge.jpg

Required mix proportion by weight

​

Basemat: 16+% urethane. 14% urethane, 86% rubber.

Top Surface: 22% urethane, 78% rubber (based on entire rubber & urethane mix).

​

Installation

​

Basemat Installation

1. Using screeds and hand towels, install the basemat mixing on a mortar mixer

to the specified thickness. Required 16% Urethane + 84% rubber.

2. Do not allow foot traffic or use of the basemat surface until it is sufficiently

cured.

​

Top Surface Installation

1. Using a hand towel and a screen bar, install top surface at mixing on a

mortar mixer 22% Urethane, 78% EPDM or TPV to a normal thickness of

.”.

2. Allow the top surface to cure for a minimum of 48 hours.

3. At the end of the minimum curing period, verify that the top surface is

sufficiently dry and firm to allow for traffic and use without damage to the

surface.

4. Do not allow foot traffic or use of the surface until it is sufficiently cured.

​

Specifier Note: Specify provisions for protecting work after installation but prior to

acceptance by the owner.

​

Protect the installed playground surface from damage resulting from subsequent

construction activity on the site.

​

Contact Details:

Office Hours

Mon - Fri

Saturday

​Sunday

8:00 am – 5:00 pm

Closed

Closed

©2021 by Malihesa Surfacing
bottom of page